Selly Oak, Birmingham
- Jay Wheeler
- Nov 24, 2017
- 1 min read
Main contractor Interserve are currently constructing a Sainsbury's supermarket, student accommodation block and several retail warehouse units in Selly Oak Birmingham.

above: a cage vibrator being used to install a full length 14m cage to a contig wall bearing pile
Lansdowne are undertaking the setting-out of the piles for client Cementation Skanska. Three rigs are currently installing the CFA piles. Lansdowne duties include generating pile co-ordinates from design drawings, setting-out, levelling cages and finally producing as-builts and red line drawings.

above: asbestos protection suits & masks being worn by piling operatives






























Comments